| Collection
Systems
The Piqua sewer system is a
separated system consisting of both sanitary wastewater and
stormwater collection piping. The existing sanitary wastewater
collection system has a service area of approximately 5500
acres. The system consists of approximately 150 miles of sewers,
ranging in size between 5" and 42" in diameter pipe.
Six (6) wastewater lift pump stations are located in the City’s
collections system. Additional sanitary wastewater flows come
from outside the City limits, being the Country Club, Monnin
Estates, The Greens at Springcreek, the I-75 Roadside rest area.
The plant operation is affected by the amount of the wastewater
flow collected by the sewers. Completion of the sewer system
rehabilitation program will eliminate inflow defects, which
currently contribute to higher then normal wastewater flows
during storm events.
Treatment
Plant History
The
existing Piqua Wastewater Treatment Plant was originally
constructed in 1957-1958. It had a nominal design capacity of
4.0 mgd and a peak-pumping rate of 7.0 mgd. The original plant
consisted of barminutors, raw sewage pumps, raw sewage metering,
chemical mix basin for feeding lime and ferric chloride, pre-aeration
basin equipped with grit collector equipment, two
(2) primary settling tanks, four (4) aeration basins, two (2)
secondary settling tanks, one (1) plant effluent pump, two (2)
anaerobic digesters with floating covers, and a sludge
dewatering vacuum filter.
In 1969, additional treatment units
were added in order to upgrade the performance of the plant. The
additional units included one (1) secondary settling tank,
chlorination building with a chlorine contact tank, and an
aerobic digester process.
In
1984, modifications were made to the existing anaerobic
digestion system, gas handling, and flow monitoring systems.
This was needed to meet the increasing and more stringent
discharge regulations. The modifications included replacement of
an existing anaerobic digester cover to a fixed lid
configuration. The gas mixing handling system was modified to
include three (3) gas bubble-mixing guns. Flow metering
equipment and modifications were added to existing primary and
secondary settling tanks.
The
1988-1989 Plant Expansion added many new tanks and equipment to
help meet the Clean Water Act Regulations of 1972. The Methane
Gas created in digestion of sludge is used to burn in the sludge
heat exchanger for the pathogen treatment of biosolids. During
this time period a new "Caterpillar" methane-burning
engine with blower was added, for the plant’s aeration
purposes and to save on electrical energy costs. Three (3) new
screw-type raw sewage pumps were added along with a new wet well
area. A new grit and grease process removal system with new flow
channels and equipment was also added. A new primary settling
tank, two (2) new aeration basins (2 passes per basin) with all
the aeration receiving four (4) new internal recycling pumps to
aid in the ammonia removal, and two (2) final settling
clarifiers (with piping and electrical for a 5th tank
expansion, if needed). The plant tunnels were expanded, all
plant mechanical HVAC and separate plant electrical power supply
feeds with a main switch – over gear were installed,
administrative offices were added and a new plant computer
operating system was installed at this time. A Centrifuge for
dewatering sludge with all associated piping and pumps were
added along with a new building to house it. Three (3) new river
pumps were added at the Post Aeration Well (pumping allows
discharge to river, even when the river level is higher than the
plant’s discharge line). Along the entire length of the plant
on the gravel pit quarry side, a retention wall was built and
the entire plant was enveloped with 6’ high chain link fence
(approx. 6 acres).
While the 1969 design of the treatment
plant was for an average daily flow of 4.0 mgd, it was not
capable of treating this amount of flow according to design
standards, and for meeting the imposed 1988 effluent permit
requirements, especially for ammonia removal.
Given the present
facilities, the flow capacity available for the treatment with
respect to the 1988 permit conditions for ammonia would be
approximately 2.5 mgd. Completion of the 1988 –1989 plant
expansion increased the average capacity to 4.5 mgd. Since
the 1988-1989 Plant upgrade, numerous modifications include
adding more equipment onto the flushing water system (recycles
the plant effluent discharge water that goes into the river and
reduces the costs of using City of Piqua treated water). A
building was erected for the grit & grease facility along
with installing a new grit classifier and rag press. A
dechlorination system was added due to EPA regulating more
stringent limits on Chlorine. A new three (3) bay Maintenance
Garage plus work area, office/storage loft, and basement for
storage has been erected and it houses a new VacCon 2-stage
(flush & vacuum) combination sewer maintenance truck,
pipeline televising camera truck, sewer maintenance jet flushing
truck, and utility pickup truck.
Current
Wastewater Treatment
A new plant
operating computer system will be installed and completed by
fall of 2001. This system will allow for all new plant
modifications, any future expansions if necessary, expanded
plant maintenance tasking, additional alarming capabilities,
sewer collection system information and lift stations statuses,
plus more operator flexibility. We are proud to be the host for
the Southwest Ohio Water Environment Association Meeting in mid-November 2001.
|