City of Piqua Ohio
City of Piqua Home PageSearch the City of Piqua SiteContact City of Piqua DepartmentsCity of Piqua Activities CalendarSite Map
 
   
Piqua Ohio Projects
2002 Streetscaping
 
Streetscaping Downtown
 
Click for Project Update as of July 17, 2002
 
Click for Project Update as of June 25, 2002
 
This project includes new curbs, sidewalks, brick pavers, decorative light posts, sign posts, benches, trash receptacles, trees, and planter boxes.  

The streetscaping includes the installation of 32 Cleveland Pear trees. Cleveland Pears are similar to Bradford Pears elsewhere in the downtown in that they are flowering trees with no fruit. However, the Cleveland variety is more columnar in shape making it suitable for streetscaping.

The contract for this project was awarded to Double Jay Construction, Englewood, Ohio, for a total cost not to exceed $650,000.  

  
The areas included in the 2002 project are:
 
Ash Street from Spring to Downing
Main Street from Water to the Linear Park
Wayne Street from Water to the Linear Park
Water Street from Wayne to Downing
 
The work, which will begin in May,  will be completed in phases to minimize the areas disrupted at any one time. Access will be provided to businesses and residential properties throughout the course of construction.  

The completion date for Ash Street is September 20, 2002.  The completion date for the Water, Wayne, and Main Street portion is December 7, 2002.

 
This project completes one more link of The Loop.  It will present an aesthetically pleasing entrance to the Central Business District and facilitate continued improvements in the downtown.  
 
Project Update - July 17, 2002
 
Work in the 200 block of West Water Street, phase three of ten, is nearing completion.  Several days were lost in this phase due to an unexpected grade conflict with 13kv primary electric lines encased in concrete.  The electric lines have been relocated to eliminate the conflict and regular streetscape work has resumed.  The installation of pavers in this block and the remainder of the 200 block of West Ash Street will be completed as soon as brick pavers are available from the supplier, possibly late next week.  The asphalt restoration in front of the curb and behind the sidewalks along West Water Street should be completed early next week.  Once this work has been performed, the work zone traffic control devices will be removed and traffic patterns restored to normal.

On July 18th work will begin on the south side of the 100 block of West Ash Street.  Like previous phases, phase four will start with the removal of the existing concrete curb and sidewalk followed by the installation of electric conduit, catch basins, concrete curbing, concrete walk and paver base, pole foundations, and the brick pavers.  This phase of Ash Street will be restricted to work being completed on the south side of the 100 block of West Ash before work on the north side of the block may begin in effort to minimize the loss of parking and inconveniences to businesses.  Also, once brick pavers have been completed in the 200 blocks of West Ash and West Water, the contractor will begin phase five in the 100 block of North Wayne Street on the east side of the street while continuing work on West Ash Street phase four.

The Engineering Department will continue to monitor the progress of the project, and as long as each phase is completed in a timely manner with minimal disruption to businesses, the contractor will continue to simultaneously work multiple phases within the project limits, in effort to accelerate the completion date of the work.
 
Project Update - June 25, 2002
 
On Monday, May 13, 2002, Double Jay Construction of Englewood, Ohio began work on the above referenced project in the 200 block of W. Ash Street.  To date 90% of the work has been completed in this block.  Remaining task include the installation of electric pull boxes, tree frames/grates, brick pavers, and asphalt restoration.  Brick paver installation should substantially complete in the 200 block of W. Ash Street by the end of this week.  The contractor will install the pavers up to the openings left where tree frames/grates and pull boxes are to be installed, and complete these areas at a later date once the tree frames/grates and pull boxes have been shipped and installed.  The asphalt restoration in front of the curb and behind the sidewalks at drive openings/parking lots should be completed early next week.

On June 20th work began on the W. Water Street portion of the project.  Concrete removal is nearly complete, with the installation of electric conduit, catch basins, concrete curb, walk, and pole foundations, and the brick pavers to follow. Once brick pavers are completed in the 200 block of W. Ash Street, the contractor will return to the Ash Street area to begin concrete demolition in the 100 block of W. Ash on the south side of the street while continuing work on the Water Street phase.  This phase of Ash Street will be restricted to work being completed on the south side of the 100 block of W. Ash before work on the north side of the block may begin in effort to minimize the loss of parking and inconveniences to businesses.

The Engineering Department will continue to monitor the progress of the project, and as long as each phase is completed in a timely manner with minimal disruption to businesses, the contractor will continue to simultaneously work multiple phases within the project limits, in effort to accelerate the completion date of the work.

 

   
  Piqua Ohio City Projects
  The Loop
  City of Piqua Ohio Bid Information
  City of Piqua Ohio
   
   
   
    
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
    
    
    
   
   
   
   
   
 
   
   
   
   
 
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
    
    
    
    
    
    
    
    
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
 
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
    
    City Projects | The Loop | Bid Information | Photos  
   Home | Search | Email | Calendar | SiteMap
   
  Copyright © 2001 by the City Of Piqua, Ohio. All rights reserved.
Reproduction in part or whole without written permission is prohibited.
This website is maintained by the City Of Piqua Information Technology Department.
Please address any questions or feedback regarding this site to the Webmaster.

Please read our Disclaimer and Privacy Statement.