Piqua Power Plant - Waterfront Redevelopment Project Update
 
Work Area Behind Power Plant
Work Area Behind Power Plant
 
The project contractor (Homrich) completed the last of the demolition and rip rap placement activities along the river bank behind the Power Plant today. As a result, the dam gates have been raised and returned to their normal summer level. Upstream water levels will continue to raise over the next few days and the normal summer river level appearance will return well in advance of next Saturday evening’s Rock Piqua event.

Homrich will be focusing on grading activities behind the Power Plant over the next week. The completion of the overlook, steps and landing along the dam will most likely be completed towards the end of July. Landscaping and seeding will happen later this fall. At this point, it is anticipated the bike path reopening behind the Power Plant in late July or early August.

  
Back to Press Releases

 

   
  City of Piqua Ohio Communications
  City of Piqua Ohio Press Releases
  Spirit Newsletter
  City of Piqua Ohio
   
    
   
     
      
     
      
    
    
   
   
   
    
   
    
    
   
   
   
   
   
   
   
   
   
      
      City Communications  | Press Releases | Piqua Spirit  
    Home | Search | Email | Calendar | SiteMap
    
  Copyright © 2001 by the City Of Piqua, Ohio. All rights reserved.
Reproduction in part or whole without written permission is prohibited.
This website is maintained by the City Of Piqua Information Technology Department.
Please address any questions or feedback regarding this site to the Webmaster.

Please read our Disclaimer and Privacy Statement.