City of Piqua Ohio
City of Piqua Home PageSearch the City of Piqua SiteContact City of Piqua DepartmentsCity of Piqua Activities CalendarSite Map
 
 
Fort Piqua Hotel Restoration -
Project Updates and Photo Gallery
   

Fort Piqua Hotel - Downtown Piqua, Ohio

Fort Piqua Hotel - Downtown Piqua

 
Hotel Project Update and Photos - April 21, 2008
  
Over the last few months, many improvements have been made on the Fort Piqua Hotel restoration project.  These improvements and projects include the installation of  lighting systems, hydronic systems, drywall, exterior restoration and other improvements.  
  
Founders Room.jpg (51780 bytes) Grid system with lights in basement.jpg (57880 bytes) Hydronic pipe.jpg (72034 bytes)
Founders Room Grid System With Lights 
(Lower Level)
Hydronic Pipes
     
more dydronic.jpg (54614 bytes) N.E. on the roof.jpg (451044 bytes) north roof.jpg (53500 bytes)
More Hydronic Pipes Northeast Portion of the Roof Looking North from the Roof
     
Old entry1.jpg (66417 bytes) Painters.jpg (44019 bytes) Plaster moulds.jpg (42098 bytes)
Old Entry Along High Street Being Restored Painters Work on the Outside Trim Plaster Molding 
     
 Roof units.jpg (51178 bytes) Second Floor Ceiling 2.jpg (53568 bytes) Second floor ceiling.jpg (45451 bytes)
Roof Units Second Floor Ceiling - Decorative Panels Installed Second Floor Ceiling
    
second floor hallway.jpg (78270 bytes) Shaft work.jpg (52515 bytes) South east.jpg (72265 bytes)
Second Floor Hallway Air Shafts Installed View of Hotel and Project Site from the Southeast
       
South, West.jpg (76927 bytes) South.jpg (69032 bytes)
View of Hotel and Project Site from the Southwest View of Hotel and Project Site from the South
      
Storefront 1.jpg (91907 bytes)   Store front work.jpg (89088 bytes)
Old Entry Along High Street Being Restored   Work on Storefront Along the South Side of the Building
 
Hotel Project Update and Photos - February 5, 2008
 
In November 2007, the contractors completed the new roof and the replacement of all of the windows in the building. This paved the way for restoration on the Ft. Piqua Hotel to focus on interior improvements. The contractors are now addressing tasks that are no longer subject to adverse weather conditions. The two areas receiving the most noticeable attention are the floors and interior walls.

Each floor has received a topping of light-weight concrete to level off the old surface and to structurally tie together the entire floor system of columns, beams and joists. The final surface can be attached directly to the light-weight concrete. Most of the floors in the building will be either carpet or floor tile, depending on the space. All of these floor coverings will enhance the historical authenticity of the building.

Sheet metal studs have been placed in many areas throughout each floor of the building. Drywall is now being installed. This is one of the biggest tasks of the job. When the project is complete it will have 1.4 acres of new drywall (61,000 sf). The building will also have 35,000 square feet of plaster topping over existing walls, as well as 22,000 square feet of ceiling tile.

 
Before and after wall restoration with windows.jpg (39559 bytes) Conduits and pipe insulation.jpg (67951 bytes) Labyrinth of of pipes, conduits, wall studs and wires.jpg (79965 bytes)
Wall & Windows Restored - 
Far Wall Still to be Restored
Conduits & Pipes 
Being Installed
Labryinth of Pipes, Conduits, Wires & Wall Studs
     
New ceiling drywall and hvac ducts.jpg (73440 bytes) New sidewalks and storefronts.jpg (76645 bytes) New studs, piping and walls.jpg (77158 bytes)
New Ceiling Drywall and 
HVAC Ducts
Sidewalk & Storefronts 
Being Repaired
New Studs, Pipes & Walls
     
New walls, floors, windows and ceiling.jpg (44200 bytes) Restoration of the old plaster.jpg (46606 bytes) Restoration of the old windows.jpg (46130 bytes)
New Walls, Floor, Ceiling & Windows Restoration of 
Old Plaster Walls
Restoration of Old Windows
     
  Second floor - new ceilings, walls and elevator.jpg (64670 bytes)
Second Floor: New Floor and Ceilings Installed -
New Elevator Shaft Can Be Seen
 
Hotel Project Update and Photos - November 19, 2007
 
Progress on the hotel restoration in October and early November has been primarily HVAC duct work, plumbing infrastructure and the roof.  Tuttle Construction demolished the old roof, placed a new roof structure and then installed a membrane finish.  GM Mechanical then connected the 13 roof drains to an intricate cast iron system of pipes down through the building to the ground floor and out to the storm sewer.  With the roof on and the windows in, the building is dry and interior restoration will begin in earnest.
 
New beams hoisted to the roof.jpg (62156 bytes) Erection of steel beams to finish roof.jpg (67162 bytes) Steel carefully place.jpg (83491 bytes)
New Beams Being 
Hoisted to the Roof
Steel Beams Being Erected to Finish Roof Placing Steel Beams Into Place
     
Beams in place.jpg (74178 bytes) roof work underway.jpg (77968 bytes) View of new roof structure from inside.jpg (69995 bytes)
Steel Beams in Place for Roof Roof Work 
(Viewed From Inside)
View of New Roof Structure 
From Inside
     
New Roof installation.jpg (70329 bytes) Fresh Paint on the exterior of the building.jpg (113240 bytes) The old skylight is exposed for restoration.jpg (96238 bytes)
New Roof Installation Fresh Paint on 
Exterior of Building
Skylight Now Exposed for Restoration
  
Hotel Project Update and Photos - October 3, 2007
 
For the past two months work on the hotel has been primarily structural improvements. The light well on the west side of the building has been replaced by structural beams, columns and LVL joists as the infill work progresses. The ground floor has been virtually completed in regards to structural steel that has been set to replace the old stone foundation walls. A tall crane with a jib was brought in to place structural steel on the roof of the structure. The contractor will soon begin replacement of the roofing materials. When that is complete and the windows are all replaced, the structure will be ready for finishes beginning on the ground floor and working upward.
 
New Structural  steel for infill.jpg (70888 bytes) Old wood work to be restored.jpg (75459 bytes) Stair tower and elevator tower from ground floor up.jpg (67924 bytes)
New Structural Steel for Infill Old Woodwork in Building - 
Will Be Restored
Stair Tower and Elevator Tower From Ground Floor
     
Windows being re-set after restoration off-site.jpg (100379 bytes) Tall crane on site to place roofing structural steel.JPG (25562 bytes) Crane towering over downtown.JPG (48940 bytes)
Windows Being Reset After Restoration Offsite Tall Crane Onsite to 
Place Roofing Structural Steel
Crane as Viewed Looking 
East on High Street
     
Water Meter Pit construction.jpg (120251 bytes) Bird's eye view of water meter pit.jpg (93991 bytes)
Water Meter Pit Construction Bird's Eye View of 
Water Meter Pit
 
Hotel Project Update and Photos - August 8, 2007
 
The Fort Piqua Hotel Restoration Project saw some exciting progress in the month of July, different from any work completed to date. Virtually all of the wall removal and structural steel on the ground floor is complete and Tuttle Construction has finished pouring most of the cast-in-place concrete floor. This will change a previously un-used space into some of the most functional space in the building, serving as the children's department and office space for the new library. In addition, metal stud walls have been placed on the new concrete slab delineating new room layouts. Metal studs have been placed on the first floor, as well.

On the second floor new LVL floor joists have been installed in what previously was a "light well" providing light and ventilation to hotel rooms that did not have exterior wall exposure. Modern artificial light and ventilation eliminates the need for light wells and the project will benefit from an additional 700 square feet of usable space on floors two, three and four.

The floor of the old kitchen on the fourth floor was found to be totally unsalvageable, and that floor has been completely rebuilt in July.

Work is nearing completion on upgrading all of the structural steel throughout the building. When that work is complete, the contractor will tear off the existing roof and rebuild a new roof system. Completion of the roof will turn the construction crews loose to begin the actual restoration of the interior, giving the building a new look very similar to its appearance in 1891. Tuttle Construction Project Manager Mike Baxter said, "At that point the project transitions from a demolition and structural engineering project to full-blown historic architectural construction."

  
To see a larger photo, click on one of the photos below:
 
Concrete block stair tower.jpg (61455 bytes) Exterior brick wall restoration on north face of building.jpg (79099 bytes) Infill of 2nd floor lightwell.jpg (92204 bytes)
Concrete Block Stair 
Tower Being Constructed
Exterior Brick Wall 
Restoration on North Face
 of Building
Infill of 2nd Floor Lightwell
     
Infill work in interior light well.jpg (88093 bytes) Metal wall studs on new concrete slab.jpg (65355 bytes) New Concrete slab on ground floor.jpg (54529 bytes)
Infill Work in Interior Lightwell Metal Wall Studs On New Concrete Slab (Lower Level) New Concrete Slab
     
New stairway on first floor.jpg (83318 bytes) Prep. work for new stair tower.jpg (73709 bytes) Rubuild floor in main lobby.jpg (67543 bytes)
New Stairway on First Floor Prep Work for New Stair Tower Rebuilding of Floor in Main Lobby
     
Structural Steel and LVLs.jpg (76630 bytes)    
Structural Steel and LVL Floor Joists    
  
 
Hotel Project Update and Photos - July 6, 2007
 
For the past two months work on the hotel has been comprised primarily of finishing up the interior demolition to pave the way for the restoration work. LVI Environmental contractor has virtually completed the asbestos removal from building, plus completed most of the wall, floor and ceiling demolition. In early May demolition work on the fourth floor re-exposed the old ballroom which had been covered up with "temporary" walls and ceilings ever since 1928. The room will soon be restored to a majestic banquet facility and conference center.

GM Mechanical has begun placing new piping in the ground floor. Carey Electric has begun channeling to provide a means for the new electric service wires and junction boxes.

Tuttle Construction has built a new stair tower in the northwest corner of the building and has also completed the majority of the new structural system in the basement, where 22" thick walls have been replaced with a new structural steel support system. Work will soon commence on the roof replacement and then the actual construction to restore the old building will begin.

  
To see a larger photo, click on one of the photos below:
 
Brick repair on west face.jpg (94193 bytes) Contractor's eye view of post office.jpg (101998 bytes) Interior controlled demolition.jpg (86087 bytes)
Brick Repair on West Side of Building View of Post Office (As Seen From Atop Hotel) Interior Controlled Demolition
     
Mini backhoe inside of building.jpg (69423 bytes) New Structural Steel.jpg (78530 bytes) New Structural Supports.jpg (88010 bytes)
Mini Backhoe Inside of Building New Structural Steel New Structural Support
     
New structural system on ground floor.jpg (74781 bytes) New wall opening, new LVL floor joists overhead.jpg (85297 bytes) Old ballroom visable - first time since 1928.jpg (72384 bytes)
New Structural System on Ground Floor New Wall Opening - New LVL Floor Joists Overhead Old Ballroom Visible - First Time Since 1928
     
Old elevator motor being removed from roof.jpg (61501 bytes) Project Architect Jeff Wray inspects the progress.jpg (70395 bytes) Remains of clock mechanism in old clock tower.jpg (111644 bytes)
Old Elevator Motor on Roof - To Be Removed Project Architect Jeff Wray Inspects the Project Remains of Clock Mechanism in Old Clock Tower
     
Storefront restoration begins on High Street.jpg (119723 bytes) Temporary timber blocking.jpg (61875 bytes) Trisco Systems employees - exterior restoration.jpg (62632 bytes)
Storefront Restoration Begins on High Street Temporary Timber Blocking Exterior Restoration 
(As Seen From Above)
 
 
Hotel Project Update and Photos - May 1, 2007
 
The old hotel was originally built in 1891.  In a restoration project one might reasonably assume that historical artifacts might be uncovered.  That has been the case during some of the interior controlled demolition.  The construction crews have unearthed items including: 
 
Cigarettes, cigars and candy advertisements
Posters
Post cards and match books
Glass plates and mugs
Ice cream scoop
2 Gideon Bibles
A tin can of "talc powder for men"
Playing cards
Wooden bus tokens
Wrist band money holders for securing valuables during sleep 
Match books
Brass tags, numbered and attached to windows for screens identification
Toledo Blade newspaper dated October 1, 1949
Pop bottle circa 1910
Sidney Brewery Beer bottle circa 1920
 
Photographs of some of the relics are shown below. All have been turned over to the Piqua Historical Museum and will be displayed from that site.

Much of the progress in the past month has consisted of removal of additional interior wall. The demolition crews started on the ground floor and they are now up to the fourth floor. Because of the demolition taking place, visitors to the building can view ballroom walls and ceiling that have not been seen since 1928. It was then that the building owners decided to turn one large room into many small hotel rooms instead.

The exterior of the building has also undergone major changes in the past month. Window frames have been scrapped and primed, and many have been painted. Furthermore, Trisco Systems, the exterior restoration contractor, is also on site and has begun the clean up and tuck-pointing of the stone outer walls.

 
To see a larger photo, click on one of the photos below:
 
Cigarette ad poster.jpg (77890 bytes) Cigar sign.jpg (81342 bytes) candyad.jpg (93539 bytes)
Cigarette Ad Poster Cigar Sign Candy Advertisement
     
old dishes cards matches and misc.jpg (92461 bytes) misc.jpg (66928 bytes) Interior Walls removed on second floor looking into Founders Room.jpg (63747 bytes)
Old Dishes, Cards, Matches & Other Miscellaneous Item Miscellaneous Item Interior Walls Removed - Looking South Towards "Founders Room"
     
 Consruction workers in safety harnesses removing fire escape.jpg (98056 bytes) Digging for new footers on the ground floor.jpg (63994 bytes)  Exterior Building restoration.jpg (83951 bytes) 
Removing the Fire Escape Digging for Footers on Ground Floor Exterior Building Restoration
       
       
Hotel Project Update and Photos - April 9, 2007
 
Work in February and March on the Fort Piqua Hotel restoration project was comprised primarily of:

Installation of safety railing throughout the building

Removal of all windows - old glazing is scraped off, the old window panes will be replaced and finally the windows will be refinished and reinstalled

Stripping the exterior window frames using a "fan-shaped" nozzle water sprayer so that the old paint is removed but the old wood is not damaged

Temporary shoring to bolster floors that need additional support during construction

Permanent Structural bolstering of the first and second floors - placement of specially engineered LVLs (Laminated Veneer Lumber) floor joists between the existing floor joists so that the structural system will support book stacks

Extensive interior demolition - virtually all of the walls and ceilings on the first and second floors that are to be removed are now gone

Removal of all interior trim, doors and base board - all will be taken off-site, refinished and replaced

Completion of asbestos removal - most of the asbestos have been on the ground floor

Install new lintels and cut openings in interior walls on the ground floor to create wide open space for development

Placement of new structural foundations in the ground floor by digging into the foundation and pouring concrete footers

Removal of all 5 floors of the old wooden stair tower in the northwest corner of the building

Removal of the old steel fire escape on the back of the building

Repair the major hole in the floor in the foyer on the main floor

Though the heavy snows and frigid temperatures delayed work temporarily, there has been major progress on the hotel during this reporting period.

  
To see a larger photo, click on one of the photos below:
 
24 inch saw - cutting through wall on ground floor.jpg (59409 bytes) 52 inch diameter saw for penetrating 24 inch foundation walls.jpg (79588 bytes) Brick housing for the old boiler that has been removed.jpg (101534 bytes)
24 inch saw - 
Cutting Through Wall on
Ground Floor
52 inch Diameter Saw for Penetrating 24 inch
 Foundation Walls
Brick Housing for the Old Boiler That has Been Removed
   
Drilling holes for new lintel.jpg (61403 bytes) Engineered LVL floor joists (yellow) placed between existing floor joists.jpg (87259 bytes) Fireplace hearths loaded for refinishing.jpg (88705 bytes)
Drilling Holes for New Lintel Engineered LVL Floor Joists (Yellow) Placed Between Existing Floor Joists Fireplace Hearths Loaded for Refinishing
     
Hoisting materials to the roof.jpg (85195 bytes) Interior demolition - west end first floor.jpg (65050 bytes) New Openings in walls on the ground floor.jpg (61227 bytes)
Hoisting Materials to the Roof Interior Demolition - 
West End of First Floor
New Openings in Walls on the Ground Floor
     
Machine parts of the old hotel elevator expsoed exposed.jpg (76860 bytes) Old Elevator - to be removed.jpg (78095 bytes)
Machine Parts of the Old Hotel Elevator Exposed Old Elevator - To be Removed
       
 
Hotel Project Update and Photos - February 20, 2007
    
Construction of the Fort Piqua Hotel restoration project commenced on January 10, 2007 as Tuttle Construction Company erected a security fence around the front of the building, setup a temporary construction trailer and began to mobilize.

For the first three months work is primarily confined to demolition by Tuttle Construction and also asbestos removal by LVI Environmental Services. LVI crews suit-up each morning in personal protective clothing with respirators and enter the containment area. The asbestos is removed, bagged and disposed of according to EPA regulations.

Because of the historical restorative nature of the work, much of the demolition involves removing materials that are to be refinished and replaced. Tuttle crews are removing the wooden trim work and interior doors so that they may be refinished and ultimately reinstalled. The twelve-foot, 600 pound mirrors on the first and second floor lobbies have also been temporarily detached and stored so that they can be refinished and eventually replaced as well.

Contractors have also begun installation of the temporary water and electrical services.

   
To see a larger photo, click on one of the photos below:
 
Constuction fence & trailer.jpg (76485 bytes) Exterior plywood protection.jpg (92917 bytes) Temporary guardrail on 2nd floor.jpg (52931 bytes)
Construction Fence and
Trailer on the Public Square
Exterior Plywood Protection Installed at Main Entrance Temporary Guardrail Installed on Second Floor
   
Staircase photo.jpg (77944 bytes) Grand staircase protected.jpg (72779 bytes) Interior Safety Measures.jpg (84794 bytes)
Grand Staircase on the First Floor Grand Staircase on First Floor Protected as Work Begins in Building Interior Safety Measures in Place
     
Installing Temporary Electrical Service.jpg (71509 bytes) LVI Evironmental crew in personal protective clothing.jpg (55088 bytes) Lifting debris from 2nd floor.jpg (77694 bytes)
Installing Temporary
 Electrical Service
LVI Environmental 
Services Crew
Lifting Debris 
From Second Floor
     
Conveyor from basement.jpg (71366 bytes) Artwork on mirror frame - to be restored.jpg (86024 bytes)
Conveyor From Basement Artwork on Mirror Frame - 
Will Be Restored
 
     
   
Fort Piqua Hotel Restoration Project
 
Hotel Renderings
 
Hotel / Library Legacy Alliance's "Restoring Piqua's Treasure" 
Fundraising Campaign
 
Photo Gallery

 

   
 
  Home | Search | Email | Calendar | SiteMap
   
  Copyright © 2001 by the City Of Piqua, Ohio. All rights reserved.
Reproduction in part or whole without written permission is prohibited.
This website is maintained by the City Of Piqua Information Technology Department.
Please address any questions or feedback regarding this site to the Webmaster.

Please read our Disclaimer and Privacy Statement.