Fort
Piqua Hotel Restoration -
Project Updates and Photo Gallery |
| |
|

|
|
Fort
Piqua Hotel - Downtown Piqua |
| |
| Hotel
Project Update and Photos - April 21, 2008 |
| |
| Over the last few
months, many improvements have been made on the Fort Piqua Hotel
restoration project. These improvements and projects
include the installation of lighting systems, hydronic
systems, drywall, exterior restoration and other improvements. |
| |
 |
 |
 |
| Founders
Room |
Grid
System With Lights
(Lower Level) |
Hydronic
Pipes |
| |
|
|
 |
 |
 |
| More
Hydronic Pipes |
Northeast
Portion of the Roof |
Looking
North from the Roof |
| |
|
|
 |
 |
 |
| Old
Entry Along High Street Being Restored |
Painters
Work on the Outside Trim |
Plaster
Molding |
| |
|
|
 |
 |
 |
| Roof
Units |
Second
Floor Ceiling - Decorative Panels Installed |
Second
Floor Ceiling |
| |
|
|
 |
 |
 |
| Second
Floor Hallway |
Air
Shafts Installed |
View
of Hotel and Project Site from the Southeast |
| |
|
|
 |
|
 |
| View
of Hotel and Project Site from the Southwest |
|
View
of Hotel and Project Site from the South |
| |
|
|
 |
|
 |
| Old
Entry Along High Street Being Restored |
|
Work
on Storefront Along the South Side of the Building |
| |
| Hotel
Project Update and Photos - February 5, 2008 |
| |
| In November 2007, the
contractors completed the new roof and the replacement of all of
the windows in the building. This paved the way for restoration
on the Ft. Piqua Hotel to focus on interior improvements. The
contractors are now addressing tasks that are no longer subject
to adverse weather conditions. The two areas receiving the most
noticeable attention are the floors and interior walls.
Each floor has received a topping
of light-weight concrete to level off the old surface and to
structurally tie together the entire floor system of columns,
beams and joists. The final surface can be attached directly to
the light-weight concrete. Most of the floors in the building
will be either carpet or floor tile, depending on the space. All
of these floor coverings will enhance the historical
authenticity of the building.
Sheet metal studs have been
placed in many areas throughout each floor of the building.
Drywall is now being installed. This is one of the biggest tasks
of the job. When the project is complete it will have 1.4 acres
of new drywall (61,000 sf). The building will also have 35,000
square feet of plaster topping over existing walls, as well as
22,000 square feet of ceiling tile. |
| |
 |
 |
 |
Wall
& Windows Restored -
Far Wall Still to be Restored |
Conduits
& Pipes
Being Installed |
Labryinth
of Pipes, Conduits, Wires & Wall Studs |
| |
|
|
 |
 |
 |
New
Ceiling Drywall and
HVAC Ducts |
Sidewalk
& Storefronts
Being Repaired |
New
Studs, Pipes & Walls |
| |
|
|
 |
 |
 |
| New
Walls, Floor, Ceiling & Windows |
Restoration
of
Old Plaster Walls |
Restoration
of Old Windows |
| |
|
|
| |
 |
|
|
Second
Floor: New Floor and Ceilings Installed -
New Elevator Shaft Can Be Seen |
|
| |
| Hotel
Project Update and Photos - November 19, 2007 |
| |
| Progress
on the hotel restoration in October and early November has been
primarily HVAC duct work, plumbing infrastructure and the roof.
Tuttle Construction demolished the old roof, placed a new roof
structure and then installed a membrane finish. GM
Mechanical then connected the 13 roof drains to an intricate
cast iron system of pipes down through the building to the
ground floor and out to the storm sewer. With the roof on
and the windows in, the building is dry and interior restoration
will begin in earnest.
|
| |
 |
 |
 |
New
Beams Being
Hoisted to the Roof |
Steel
Beams Being Erected to Finish Roof |
Placing
Steel Beams Into Place |
| |
|
|
 |
 |
 |
| Steel
Beams in Place for Roof |
Roof
Work
(Viewed From Inside) |
View
of New Roof Structure
From Inside |
| |
|
|
 |
 |
 |
| New
Roof Installation |
Fresh
Paint on
Exterior of Building |
Skylight
Now Exposed for Restoration |
| |
| Hotel
Project Update and Photos - October 3, 2007 |
| |
| For the past two
months work on the hotel has been primarily structural
improvements. The light well on the west side of the building
has been replaced by structural beams, columns and LVL joists as
the infill work progresses. The ground floor has been virtually
completed in regards to structural steel that has been set to
replace the old stone foundation walls. A tall crane with a jib
was brought in to place structural steel on the roof of the
structure. The contractor will soon begin replacement of the
roofing materials. When that is complete and the windows are all
replaced, the structure will be ready for finishes beginning on
the ground floor and working upward. |
| |
 |
 |
 |
| New
Structural Steel for Infill |
Old
Woodwork in Building -
Will Be Restored |
Stair
Tower and Elevator Tower From Ground Floor |
| |
|
|
 |
 |
 |
| Windows
Being Reset After Restoration Offsite |
Tall
Crane Onsite to
Place Roofing Structural Steel |
Crane
as Viewed Looking
East on High Street |
| |
|
|
 |
 |
|
| Water
Meter Pit Construction |
Bird's
Eye View of
Water Meter Pit |
|
| |
| Hotel
Project Update and Photos - August 8, 2007 |
| |
| The Fort
Piqua Hotel Restoration Project saw some exciting progress in
the month of July, different from any work completed to date.
Virtually all of the wall removal and structural steel on the
ground floor is complete and Tuttle Construction has finished
pouring most of the cast-in-place concrete floor. This will
change a previously un-used space into some of the most
functional space in the building, serving as the children's
department and office space for the new library. In addition,
metal stud walls have been placed on the new concrete slab
delineating new room layouts. Metal studs have been placed on
the first floor, as well.
On the second floor new LVL floor
joists have been installed in what previously was a "light
well" providing light and ventilation to hotel rooms that
did not have exterior wall exposure. Modern artificial light and
ventilation eliminates the need for light wells and the project
will benefit from an additional 700 square feet of usable space
on floors two, three and four.
The floor of the old kitchen on
the fourth floor was found to be totally unsalvageable, and that
floor has been completely rebuilt in July.
Work is nearing completion on
upgrading all of the structural steel throughout the building.
When that work is complete, the contractor will tear off the
existing roof and rebuild a new roof system. Completion of the
roof will turn the construction crews loose to begin the actual
restoration of the interior, giving the building a new look very
similar to its appearance in 1891. Tuttle Construction Project
Manager Mike Baxter said, "At that point the project
transitions from a demolition and structural engineering project
to full-blown historic architectural construction." |
| |
| To see a larger photo, click on
one of the photos below: |
| |
 |
 |
 |
Concrete
Block Stair
Tower Being Constructed |
Exterior
Brick Wall
Restoration on North Face
of Building |
Infill
of 2nd Floor Lightwell |
| |
|
|
 |
 |
 |
| Infill
Work in Interior Lightwell |
Metal
Wall Studs On New Concrete Slab (Lower Level) |
New
Concrete Slab |
| |
|
|
 |
 |
 |
| New
Stairway on First Floor |
Prep
Work for New Stair Tower |
Rebuilding
of Floor in Main Lobby |
| |
|
|
 |
|
|
| Structural
Steel and LVL Floor Joists |
|
|
| |
| |
| Hotel
Project Update and Photos - July 6, 2007 |
| |
| For the past two months work on the hotel has been
comprised primarily of finishing up the interior demolition to
pave the way for the restoration work. LVI Environmental
contractor has virtually completed the asbestos removal from
building, plus completed most of the wall, floor and ceiling
demolition. In early May demolition work on the fourth floor
re-exposed the old ballroom which had been covered up with
"temporary" walls and ceilings ever since 1928. The
room will soon be restored to a majestic banquet facility and
conference center.
GM Mechanical has begun placing new piping in the ground
floor. Carey Electric has begun channeling to provide a means
for the new electric service wires and junction boxes.
Tuttle Construction has built a new stair tower in the northwest
corner of the building and has also completed the majority of
the new structural system in the basement, where 22" thick
walls have been replaced with a new structural steel support
system. Work will soon commence on the roof replacement and then
the actual construction to restore the old building will begin. |
| |
| To see a larger photo, click on
one of the photos below: |
| |
 |
 |
 |
| Brick
Repair on West Side of Building |
View of
Post Office (As Seen From Atop Hotel) |
Interior
Controlled Demolition |
| |
|
|
 |
 |
 |
| Mini
Backhoe Inside of Building |
New
Structural Steel |
New
Structural Support |
| |
|
|
 |
 |
 |
| New
Structural System on Ground Floor |
New
Wall Opening - New LVL Floor Joists Overhead |
Old
Ballroom Visible - First Time Since 1928 |
| |
|
|
 |
 |
 |
| Old
Elevator Motor on Roof - To Be Removed |
Project
Architect Jeff Wray Inspects the Project |
Remains
of Clock Mechanism in Old Clock Tower |
| |
|
|
 |
 |
 |
| Storefront
Restoration Begins on High Street |
Temporary
Timber Blocking |
Exterior
Restoration
(As Seen From Above) |
| |
| |
| Hotel
Project Update and Photos - May 1, 2007 |
| |
| The old hotel was
originally built in 1891. In
a restoration project one might reasonably assume that
historical artifacts might be uncovered.
That has been the case during some of the interior
controlled demolition. The
construction crews have unearthed items including: |
| |
| •
Cigarettes, cigars and candy advertisements |
| •
Posters |
| •
Post cards and match books |
| •
Glass plates and mugs |
| •
Ice cream scoop |
| •
2 Gideon Bibles |
| •
A tin can of "talc powder for men" |
| •
Playing cards |
| •
Wooden bus tokens |
| •
Wrist band money holders for securing valuables
during sleep |
| •
Match books |
| •
Brass tags, numbered and attached to windows for
screens identification |
| •
Toledo Blade newspaper dated October 1, 1949 |
| •
Pop bottle circa 1910 |
| •
Sidney Brewery Beer bottle circa 1920 |
| |
| Photographs of some of
the relics are shown below. All have been turned over to the
Piqua Historical Museum and will be displayed from that site.
Much of the progress in the past
month has consisted of removal of additional interior wall. The
demolition crews started on the ground floor and they are now up
to the fourth floor. Because of the demolition taking place,
visitors to the building can view ballroom walls and ceiling
that have not been seen since 1928. It was then that the
building owners decided to turn one large room into many small
hotel rooms instead.
The exterior of the building has
also undergone major changes in the past month. Window frames
have been scrapped and primed, and many have been painted.
Furthermore, Trisco Systems, the exterior restoration
contractor, is also on site and has begun the clean up and
tuck-pointing of the stone outer walls. |
| |
| To see a larger photo, click on
one of the photos below: |
| |
 |
 |
 |
| Cigarette
Ad Poster |
Cigar
Sign |
Candy
Advertisement |
| |
|
|
 |
 |
 |
| Old
Dishes, Cards, Matches & Other Miscellaneous Item |
Miscellaneous
Item |
Interior
Walls Removed - Looking South Towards "Founders Room" |
| |
|
|
 |
|
|
|
|
|
| Removing
the Fire Escape |
Digging
for Footers on Ground Floor |
Exterior
Building Restoration |
| |
|
|
| |
| Hotel
Project Update and Photos - April 9, 2007 |
| |
| Work in February
and March on the Fort Piqua Hotel restoration project was
comprised primarily of:
Installation of safety railing
throughout the building
Removal of all windows - old glazing is scraped off, the old
window panes will be replaced and finally the windows will be
refinished and reinstalled
Stripping the exterior window frames using a
"fan-shaped" nozzle water sprayer so that the old
paint is removed but the old wood is not damaged
Temporary shoring to bolster floors that need additional support
during construction
Permanent Structural bolstering of the first and second floors -
placement of specially engineered LVLs (Laminated Veneer Lumber)
floor joists between the existing floor joists so that the
structural system will support book stacks
Extensive interior demolition - virtually all of the walls and
ceilings on the first and second floors that are to be removed
are now gone
Removal of all interior trim, doors and base board - all will be
taken off-site, refinished and replaced
Completion of asbestos removal - most of the asbestos have been
on the ground floor
Install new lintels and cut openings in interior walls on the
ground floor to create wide open space for development
Placement of new structural foundations in the ground floor by
digging into the foundation and pouring concrete footers
Removal of all 5 floors of the old wooden stair tower in the
northwest corner of the building
Removal of the old steel fire escape on the back of the building
Repair the major hole in the floor in the foyer on the main
floor
Though the heavy snows and frigid
temperatures delayed work temporarily, there has been major
progress on the hotel during this reporting period. |
| |
| To see a larger photo, click on
one of the photos below: |
| |
 |
 |
 |
24 inch saw -
Cutting Through Wall on
Ground Floor |
52 inch
Diameter Saw for Penetrating 24 inch
Foundation Walls |
Brick
Housing for the Old Boiler That has Been Removed |
| |
|
|
 |
 |
 |
| Drilling
Holes for New Lintel |
Engineered LVL
Floor Joists (Yellow) Placed Between Existing Floor Joists |
Fireplace
Hearths Loaded for Refinishing |
| |
|
|
 |
 |
 |
| Hoisting
Materials to the Roof |
Interior
Demolition -
West End of First Floor |
New Openings in
Walls on the Ground Floor |
| |
|
|
 |
|
 |
| Machine
Parts of the Old Hotel Elevator Exposed |
|
Old Elevator -
To be Removed |
| |
|
|
| |
| Hotel
Project Update and Photos - February 20, 2007 |
| |
|
Construction of the Fort Piqua Hotel
restoration project commenced on January 10, 2007 as Tuttle
Construction Company erected a security fence around the front
of the building, setup a temporary construction trailer and
began to mobilize.
For the first three months work
is primarily confined to demolition by Tuttle Construction and
also asbestos removal
by LVI Environmental Services. LVI crews suit-up each morning in
personal protective clothing with respirators and enter the
containment area. The asbestos is removed, bagged and disposed
of according to EPA regulations.
Because of the historical
restorative nature of the work, much of the demolition involves
removing materials that are to be refinished and replaced.
Tuttle crews are removing the wooden trim work and interior
doors so that they may be refinished and ultimately reinstalled.
The twelve-foot, 600 pound mirrors on the first and second floor
lobbies have also been temporarily detached and stored so that
they can be refinished and eventually replaced as well.
Contractors have also begun
installation of the temporary water and electrical services.
|
| |
| To see a larger photo, click on
one of the photos below: |
| |
 |
 |
 |
Construction
Fence and
Trailer on the Public Square |
Exterior
Plywood Protection Installed at Main Entrance |
Temporary
Guardrail Installed on Second Floor |
| |
|
|
 |
 |
 |
| Grand
Staircase on the First Floor |
Grand
Staircase on First Floor Protected as Work Begins in Building |
Interior
Safety Measures in Place |
| |
|
|
 |
 |
 |
Installing
Temporary
Electrical Service |
LVI
Environmental
Services Crew |
Lifting
Debris
From Second Floor |
| |
|
|
 |
 |
|
| Conveyor
From Basement |
Artwork
on Mirror Frame -
Will Be Restored |
|
| |
|
|