County Road 25-A Reconstruction Project -
Project Updates and Photo Gallery
   
   
Project Update and Photos- Late September 2007
 
The Contractor, R.B. Jergens out of Vandalia, Ohio, set the Prestressed Concrete I-beams for the bridge over Rush Creek as a part of the CR 25-A Reconstruction Project. 

A total of 39 bridge beams were set during the two day timeframe. Of the 39 beams, 26 beams were 43'-2 1/2" in length and 13 beams were 62'-5" in length. All of the beams are 3' tall. The overall length of the bridge is 148'-10" and the overall deck width is 82'.
 
To see a larger photo, click on one of the photos below:
 
IMG_1761.JPG (65589 bytes) IMG_1764.JPG (72046 bytes) IMG_1767.JPG (81897 bytes)
Crane Setting Beam in Place Workers Await Next Beam  Moving Beam into Position
     
IMG_1770.JPG (81748 bytes) IMG_1773.JPG (80583 bytes) IMG_1781.JPG (83575 bytes)
Another Beam One of the 39 Bridge Beams Being Set Each Beam was Delivered by Truck
     
IMG_1783.JPG (77320 bytes)  IMG_1788.JPG (93307 bytes) IMG_1789.JPG (64588 bytes)  
Setting the Beam in Place   Crane Setting Beam in Place  
       
IMG_1787.JPG (76180 bytes) IMG_1785.JPG (95451 bytes)
Another Beam Swings into Position Guiding the Beam into the Proper Position
 
 
Project Update and Photos- August 6, 2007
 
The Contractor, R.B. Jergens out of Vandalia, Ohio has completed the pavement removal on the north side of CR 25-A. Two-way traffic is being maintained on the south side of CR 25-A on the new "temporary" pavement. The Contractor is also continuing the installation of the 20" water main, which will be located underneath the southbound lanes of travel once the final pavement is in place. The service laterals will need to be installed and the water main will need to be tested and chlorinated prior to the new main being put into service. The schedule is to make the transition from the old water main to the new water main sometime mid to late August.

The Contractor is also in the process of replacing the bridge over Rush Creek. The majority of the existing structure has been removed. The Contractor is gearing up to begin driving piling for Pier #2 (east side). Once the pile driving is complete, the Contractor will begin pouring concrete for the footer for Pier #2.

The Contractor has removed the concrete median and has begun widening the pavement on the south side of Rush Creek towards the river bridge. Storm sewer installation is also taking place on the south side of Rush Creek.

 
To see a larger photo, click on one of the photos below:
 
25A Construction august 001.jpg (101415 bytes) 25A Construction august 002.jpg (76280 bytes) 25A Construction august 003.jpg (116917 bytes)
Preparing for Pile Driving for Piers Driving Pile  Driving Pile for Pier
     
25A Construction august 004.jpg (99511 bytes) 25A Construction august 005.jpg (115644 bytes) 25A Construction august 006.jpg (54667 bytes)
New 20" Water Line Work Working on Installing 20" Water Line Water Line Installation Work
     
25A Construction august 007.jpg (54370 bytes)     
Working on Installation of 20" Water Line     
 
 
Project Update and Photos - July 10, 2007
 
The Contractor, R.B. Jergens out of Vandalia, Ohio has completed the installation of the temporary pavement and the storm sewer on the south side of CR 25-A. Traffic was switched over to this temporary pavement on the south side of CR 25-A on Monday, July 2, 2007. R.B. Jergens has begun removing the existing pavement on the north side and installing new storm sewer on the north side. The installation of the new 20" water main will also take place during this phase of work.

The replacement of the bridge over Rush Creek will also take place during this phase. During the bridge replacement, CR 25-A between Hetzler Road and Piqua-Lockington Road will be closed to all traffic. The official closure of CR 25-A between Hetzler Road and Piqua-Lockington Road began Monday, July 9, 2007.

The construction of the bridge is anticipated to take approximately 120 days. An official detour will be set up to direct traffic around the road closure which will consist of: Looney Road to U.S. Rt. 36 and then back onto CR 25-A.

As with all construction projects, motorists are asked to proceed through the construction areas with caution

  
To see a larger photo, click on one of the photos below:
 
25A 001.jpg (62677 bytes) 25A 002.jpg (61527 bytes) 25A 006.jpg (86273 bytes)
June 29, 2007
Placing Temporary Pavement at Sherry Drive
June 29, 2007
Temporary Pavement
June 29, 2007
Installing 48" Storm Sewer
South of Hetzler Road
     
25A 007.jpg (74163 bytes) 25A 008.jpg (82668 bytes) 25A 010.jpg (90206 bytes)
July 3, 2007
Removing Median at Rush Creek
July 3, 2007
Placing Barrier Wall
July 9, 2007
Beginning Tap of 16" Water Main at North Dixie Drive
     
25A 011.jpg (70355 bytes) 25A 012.jpg (51337 bytes)  
July 9, 2007
Excavating Old Pavement 
at Hetzler Road
July 9, 2007
Excavating Old Pavement
at VFW
 
  
 
 Photo Gallery
  
Back to City of Piqua Home Page 

 

   
 
  Home | Search | Email | Calendar | SiteMap
   
  Copyright © 2001 by the City Of Piqua, Ohio. All rights reserved.
Reproduction in part or whole without written permission is prohibited.
This website is maintained by the City Of Piqua Information Technology Department.
Please address any questions or feedback regarding this site to the Webmaster.

Please read our Disclaimer and Privacy Statement.